Global Data Center Separation
Challenge
A divested business had to exit its parent's data centers across three regions onto a standalone hosted platform, with Day 1 readiness contractually fixed to the close date.
Scope Owned
Owned application and dependency analysis across the client's ERP and business application estate, the data migration strategy, and the cutover sequencing. Coordinated the technical workstream across client, parent and third-party teams through to Go-Live.
Outcomes
- 800+ virtual machines migrated across North America, Europe and India
- Go-Live executed in a 28-hour window with zero technology incidents
- 100% of data migrated
- Day 1 readiness delivered against a contractual close date
- 99.79% uptime sustained across the five-year term that followed